Problems again stall production from Santos' $6.8b Barossa LNG
Santos is battling blocked heat exchangers, failed subsea valves, and faulty safety doors 285km north of Darwin so it can reap the reward of high gas prices in Asia.
The Darwin LNG plant has processed gas from the Bayu Undan field in Timor-Leste waters since 2006. Operator Santos plans to switch to processing gas from the Barossa field in 2025.
The troubled $6 billion flagship will be out of action "for a number of weeks," just as Santos' customers are desperate for gas to replace supply from the Middle East.
Australian LNG producers are under pressure on emissions and decommissioning, and Santos wants to tackle both problems in one swoop at Bayu Undan, but it needs everyone to play along.
Santos and ENI are looking for solutions for CO2 and removing old facilities in the waters north of Darwin. Time will tell if the problems are solved or just delayed.